March 2025

N74 Fr. Mathew Street Renewal Project: Traffic Management Update N24 Bansha Road Roundabout: Phase 1 and Phase 2 of these works are complete Phase 3 works shall commence on Monday 24th March and are expected to be complete by Friday 28th March. As per the previous phases a Stop / Go temporary traffic signal system will be in place. The traffic signals will be operated manually during work hours and will operate on a timer outside of work hours. It is anticipated that the temporary traffic signal system will be removed from the roundabout at lunchtime Friday 28th March. Cashel Road: The temporary traffic signals will be in place from Monday 24th March to Friday 28th March. Fr. Mathew Street One-Way System: The one-way system is to remain in operation until the completion of the scheme.