Further to the issue of flyer no.2 on the 06th of June 2024, the contractor GLAS Civil Engineering Limited has continued the works on the scheme. The following works are ongoing:
• Offline surface water drainage works are nearing completion at the rear of Sean Allen Terrace/Knockanrawley Road.
• New surface water drainage works are ongoing past the graveyard.
• Watermain Installation is 75% complete.
• New EIR ducting and chamber installations are ongoing.
• Laying of new limestone kerbs and pouring of concrete footpaths are ongoing along Fr Mathew Street on the RHS.
• New pedestrian crossing layout is under construction outside Maxol service station.
See gallery for “N74 Fr. Mathew Street, Tipperary Town Road Improvement Scheme” – Flyer no. 3